Case Study

Boosting the automotive industry with sustainable energy solutions in the state of San Luis Potosí

San Luis Potosí, México

Hot Air icon

Electricity

Electricity generation

Hot Air icon

Cold water

Water cooling

CONSUMPTION
26,972,040 (100%)
GENERATION
21,269,280 (78.86%)

INSTALLED EQUIPMENT

3 Microturbinas C1000S y 1 Microturbina C600S

FUEL

Gas natural

RESULS

78% savings in energy consumption

Description

DTC Solutions and the automotive industry joined forces in search of a solution for the power supply system, which in addition to helping them to reduce costs, would also have an environmental benefit by reducing their polluting emissions.

According to the data provided, it was found that the average energy consumption is 3,079 Kw respectively, so the plant would need the installation of 3 Capstone C1000 and 1 C600 Microturbines to cover 78% of its electricity consumption and 95% of its billable demand.